In 2013 we were given the contract to build the skatepark for the charity group 4 motion in Darlington.
This build presented a few challenges due to the relatively small budget and vast size of the unit purchased. We had a hard time filling the space with enough interesting obstacles and keeping to the budget. the result was pretty good tho as we slimmed down our on site work force and worked long days. The two of us on site completed the build in 18 weeks.
We used the following:
9 miles of 4×2
90,000 screws
and about 1200 sheets of different plys.